15 October 2019: Minor Repairs to Clary Lake Dam Completed

20191015_105109_compressedLast spring when the water level reached the top of the Clary Lake dam we discovered a few leaks that were missed during major repairs last fall. There were three gaps between stones near the south end of the dam by the red building, obscured by vegetation, and one small hole at the north end of the dam. At the time we just used sandbags to staunch the flow and made plans to repair the leaks properly this fall when the lake level was down.

We began the fall draw down back in mid-September and as of today the lake was 1 foot below the HWM, plenty low enough to allow us to make the repairs. Two bags of high strength Quickrete mortar mix and an hour and a half and we were done. Many thanks to Dam Operations Committee members Dave Knight and Steve Cowles for helping out with this project! Here are a few pictures from this morning’s work:

One thought on “15 October 2019: Minor Repairs to Clary Lake Dam Completed

Comments are closed.